Se prevé que pronto comiencen las perforaciones geotérmicas en Szczecin, Polonia
Han comenzado los preparativos en el lugar para las perforaciones geotérmicas previstas en Szczecin, Polonia; se espera que los trabajos de perforación den comienzo hacia finales de año.
Site preparations is ongoing and parts of the drilling rig are expected to be delivered on site by November or December as part of the preparatory work for geothermal drilling in the city of Szczecin in Poland. The actual drilling is expected to start at the turn of the year and will last approximately three months.
Szczecin was one of the territories that were selected to receive funding by Poland’s Ministry of Climate and Environment thru the National Fund for Environmental Protection and Water Management (NFOSiGW) for geothermal heating projects, as announced back in 2023. The grant agreement, signed in December 2024, awards PLN 12.9 million (approx. USD 3.2 million) intended to cover the costs related to drilling.
In 2025, the city signed contracts with Multiconsult Polska Sp. z o.o. and UOS Drilling SA, for supervisory work and drilling services for the project, respectively.
The Szczecin GT-2 well is planned to be drilled to a depth of 1950 meters, targeting Upper Triassic formations. Based on previous studies, the geothermal resource hosted in this formation will have temperatures of 70 – 75 ºC, and support a flow rate of 200 m3/hr. The test borehole will serve to help assess if the resource will support geothermal heating supply in Szczecin.
Drilling had initially been scheduled to start by mid-2026. However, UOS Drilling submitted a request for a schedule revision due to delays resulting from the need to adapt the project to actual site conditions. This meant changing the location of the planned well within the plot and modifying the layout of the drill site.
According to the city, the submission of the remedial plans did not provide a legal basis for amending the contract with the service provider or extending the implementation period which was originally set to end by 3 December 2026. However, the documents have been treated by the investor (the Szczecin City Commune) as confirmation of the intent of the contractor to complete the work. Nevertheless, the investor has retained the full right to charge contractual penalties.
Source: Wiadomosci Szczecin